Environmental Remediation Projects
Gordo
The Gordo property has been enrolled in an Environmental Cleanup since 2022. The contaminated material was removed in 2023 and a Site Management Plan has been developed. Prior to adopting the plan, a draft is available for public comment beginning on November 10, available here. A full project timeline is available below:
Gordo-related staff reports, documents, and timeline below:
- Fall 2021- City abandons Soil Repository for Gordo
- September 2022 - Council gives direction to enter into a clean up program with DEQ | City Council Staff Report
- October 2022 - City enters into the Environmental Clean Up Program with DEQ
- March 2023 - Consultant Selected, Terracon Consultants, LLC | City Council Staff Report
- July 2023 - Comprehensive site sampling
- November 2023 - Final Site Characterization and Risk Assessment Report is submitted to DEQ | Council Retreat September 2023 Gordo Update
- December 2023 - Site Characterization and Risk Assessment Report is approved by DEQ DSHW-2023-212289
- Q1 2024 - Development of Corrective Action Plan
- February 27, 2024 Corrective Action Plan approved by Utah DEQ | Approval Letter
- May 16, 2024 City Council Approves contracts for site excavation and environmental oversight
- June 17, 2024 Estimated start date for remediation | Remediation contact: Ryan Blair, 385-290-7703
- Planned November 2024 Site fully remediated
-
Planned Winter 2025 Development of site management plan and site closure by Utah DEQ
Bonanza Park Brownfield Grant Award
- Grant is funded by EPA/DEQ
- The work is contracted through DEQ
- 18 boreholes
- Funds provide opportunity to test both soil and groundwater
- Wide range of sampling parameters
- January 2024 City Council Staff Report
- Brownfield Cleanup Alternatives Report
- Bonanza Park FY25 Brownfield Cleanup Grant Application - Public Comment Draft